Summit Township 2018 Road Projects

Township Wide Dust Control for 2.36 Miles.  One single application. Total Cost $600.00.

Hawley Road from Pere Marquette Hwy Westerly to Cul-de-sac for .77 miles.  Crack Seal, chip and fog seal.  Total cost $20,850.00.

Anderfind Road from NW of Meisenheimer Road for 50 feet.  Place HMA wedge for spot repair settlement.  Total cost $3,650.00.

Olmstead Road from Lakeshore Dr easterly to end of pavement for .45 miles. Upgrade Cul-de-sac with slag and place HMA.  Total cost $29,750.00.